Learn, practise, revise
Time and work: combine rates, then find the remaining work
Convert each worker’s completion time to a rate. Add rates only while those workers are actually working together.
The method
Work completed = rate × time. Combined rate = 1/a + 1/b jobs per day.
पहले आधार या दर पहचानें। फिर सवाल हल करें और उत्तर को मूल जानकारी से जाँचें।
A finishes a job in 12 days and B in 18 days. How long together?
Combined rate = 1/12 + 1/18 = 5/36 job/day. Time = 36/5 = 7.2 days.
A needs 18 days, B needs 24 days. They work together for six days, then A leaves. How much longer does B need?
Take total work as 72 units. Daily rates are 4 and 3 units. Together they do 42 units in six days. B completes the remaining 30 units in 30/3 = 10 more days.
A common mistake
Do not average completion times. Time and rate are reciprocals. Check who works in each interval.
Now practise and review
Targeted practice requires free sign-in and follows the displayed daily allowance. A link selects the topic; it never starts a test or consumes quota by itself.
Frequently asked questions
Are these official SSC previous-year questions?
No. These examples are original worked practice. Official-paper provenance is shown separately for archived PYQs.
Practice material, not an official SSC publication. About the project · How questions are checked